Reminder: Traffic Delays on State Route 147 as Culvert Project Enters Second Phase

SHARE NOW

The Westwood Beach Culverts Project is now in its second phase, affecting traffic along State Route 147 near Canyon Dam. This $600,000 project by Caltrans District 2 aims to rehabilitate aging culverts at eight locations, stretching from just south of Indian Hills Road to north of County Road A-13.

What to Expect This Week:

  • Today, Monday, September 23rd: Crews will be conducting sampling work, which may cause delays of up to 30 minutes between 7 a.m. and 5 p.m.
  • Tuesday and Friday: Expect similar delays as sampling continues throughout the week.

Looking Ahead: Excavation work will resume in mid-October with one-way traffic control, causing delays of up to 15 minutes during weekdays from 7 a.m. to 5 p.m.
Plan for extra travel time and be mindful of reduced speed limits and construction crews in the area. The project is expected to be completed by the end of October.